C18.2. The duration and extent of any interruption of any part of the Registry Function.

If the first migration plan is selected (Plan A under C18.1), there will be no interruption of service.

If the second migration plan is selected (Plan B under C18.1), the registry will be available in read-only mode during the data migration from VeriSign to Unity Registry. This option is expected to take two days, and would be performed over a weekend.